Construction Update
Q3 2026
Construction advanced steadily on both towers through the third quarter. The hotel reached a key design milestone, and the residences tower completed its concrete structure.
Hotel Tower
- The hotel model room has been completed and reviewed by Four Seasons. Finishes have been approved and are now in fabrication.
- The concrete structure continues to rise. More than 40,500 cubic yards of concrete and 5,000 tons of rebar have been placed to date.
- Curtain wall installation is underway, and exterior framing and sheathing are progressing.
- Mechanical, electrical and plumbing (MEP) rough-in and masonry work continue on the lower levels.
- The tower is expected to top out by the end of the year.
Residences Tower
- The concrete structure is complete.
- Curtain wall panels have been installed on levels 4 through 9, and roof waterproofing has begun.
- Interior framing, MEP rough-in and fire sprinkler installation are progressing on multiple floors.
- The tower remains on track to be fully enclosed by the end of the year.